This roof has two sections, each with a built up roof (BUR) with gravel system that had been repaired multiple times in the past.
| |
|  |
| |
|  |
The gravel was removed, along with the old roof system to allow us to fully inspect the wood substrate for damage.
| Equipment and material being loaded.
|
|  |
After any necessary replacement, the substrate is prepared for installation of new IB Roof System CPA single ply membrane.
| |
|  |
Installation of the new single ply membrane in progress. Mechanically fastened with hot air welded seams.
| |
|  |
Project near completion on this upper section.
| |
|  |
| |
|  |
Project completion pictures. New IB Roof System 80 mil CPA single ply membrane system over ISO rigid insulation.
| |